Ian and Jay replaced wood decking with composite decking in Waltham.

Marvin, Alex and Alfredo worked in West Roxbury.  They finished installing the Durock.  The foundation walls are now ready for scratch coating.  The men worked on the decks and siding as well.  They installed aluminum flashing along the ledger (to prevent water from getting behind it) and installed jchannels all around the frame as well as around the windows and doors.  They made quite a bit of progress siding the wall as well.

Tomorrow they’ll install the structural posts and frame the stairs.  The inspector will be coming by at around noon for the framing inspection!