West Roxbury – Final Touches

This week we’ve completed veneering one side of the foundation and finished building the deck.  We installed the DrySnap system underneath the top deck which will direct rain and melting snow into a gutter and through the downspout.  This way the bottom deck stays dry!  Check out the drysnap system at www.drysnap.com – it’s reasonably priced and relatively easy to install.  Tomorrow we’ll install the storm doors and form the bulkhead steps in preparation for pouring.